Neilcott Construction Limited

BARKING ABBEY SCHOOL

Occupied Site

Steel Frame

Decant

Phasing

Info box:

Client: London Borough of Barking and Dagenham
Architect: Rivington Street Studio
Quantity Surveyor: Playle and Partners
Project Manager: BeFirst
Value: £19.2m

Developed from RIBA Stage 3 through a 2-stage design and build process, we managed this project to expand the school across three separate sites in Barking.

New buildings provide; 2,450m2 of specialist teaching accommodation and a new sixth form centre at the Sandringham campus, 3,200m2 of specialist teaching accommodation and a new kitchen and dining hall at the Longbridge campus and 1,300m2 of sporting and community facilities on its sports area.

Site 1 – Longbridge Road Campus

This new steel framed teaching block has an attractive red brick façade and incorporates the following new facilities:

  • General teaching, science labs, art and design/technology classrooms
  • Dining hall and kitchen facilities
  • Staff room, offices, toilets and support accommodation

Site 2 – Longbridge Road Campus Sports Building

A design review changed the location of the building to avoid large groups of students having to cross a busy road to access the new sports facilities. The new single-storey steel frame sports block was designed to be:

  • Compliant to Sports England guidelines to maximise revenue generation/external use
  • Sized to accommodate 2 new sports courts

Site 3 – Sandringham Campus, New Classrooms and Sixth Form Centre

New steel framed classroom block and sixth form centre connected to an existing building through circulation space to provide a seamless link at ground and first floors. Existing temporary accommodation on-site was removed following completion of the new building.

  • New sixth form centre, comprising open plan study area, ICT suite, separate reception, offices
  • Kitchen/servery
  • 4 science labs

Additional works were instructed during the contract including refurbishment of an existing 1920s hall and new car parking.

“Neilcott spend time to understand our goals and end user requirements to help the whole team achieve these shared project objectives. They have a non-confrontational approach and work constructively to find solutions and ways to add value.”                  Dawn Hughes – Senior Project Sponsor