MANOR LONGBRIDGE PRIMARY SCHOOL
CLT
Accelerated Programme
BREEAM Excellent
Info box:
Client: London Borough of Barking and Dagenham
Value: £9m
Neilcott were appointed to undertake the design and construction of a new 3 form entry primary school on Longbridge Road including associated external works and drainage.
The works had to be completed in two sections with 60% of the school being handed over in 21 weeks. The primary school was designed to achieve a BREEAM Excellent rating. The building energy requirements were driven down by the increased efficiency of the thermal insulation. Air permeability, high efficiency luminaries with presence detection and daylight dimming facility, passive ventilation strategy and MVHR where mechanical extract was required all added to the buildings sustainability credentials.
The soft landscaping incorporated a planting scheme design in conjunction with our ecologist in order to promote biodiversity and create a learning zone for the students together with an allotment which relied upon rainwater for watering.
A SUDS/infiltration storm water drainage system was designed so that previous loading to the Thames Water sewers could be reduced.
The Manor Longbridge Primary School is an exemplary sustainability model both in terms of construction and operation. Using lessons learnt from previous cross laminated timer structures, Neilcott were able to reduce programme time and reduce cost whilst maintaining an excellent level of quality.